§ 86-174. Large projects.  


Latest version.
  • (a)

    Public Service Commission Rule 515-9-4.13 Procedures for Large Projects shall be followed.

    (b)

    The large marking agreement referenced in Public Service Commission Rule 515-9-4-13 must describe the scope of the project. The large project marking agreement must divide the project into sections and assign "locate by" and "excavation by" dates for each section.

    (c)

    Changes to the large project marking agreement must be in writing, i.e., hard copy or email.

( Ord. No. 0-15-15, art. I , 8-6-15)